DHI Water Transfer Job Quantifier

DHI Water Transfer Job Quantifier

Internal estimator for scoping, hydraulic sanity checks, equipment quantity, operating cost, and proposal pricing. Green cells are editable inputs.

Saved Local Jobs

Local save stores the input parameters only, not calculated results. It is saved in this browser under the DHI water transfer estimator key.

1. Job Identification

CustomerJob Name
Project LocationPrepared By
Estimate DateRevision
StatusFuel Included?
Scope Notes

2. Scope Inputs

Target FlowBPM
Operating Daysdays
Rig-Up Daysdays
Rig-Down Daysdays
Route Lengthlinear miles
Parallel Linescount
Hose / Pipe IDinches
Elevation Changefeet
Road Crossingscount
Produced Water SGwater = 1.00

3. Hydraulic Sanity Check

Hazen-Williams Clayflat/poly typical range varies by condition
Pump Modeldescription
Pump HorsepowerHP each
Pump Efficiencydecimal
Assumed Max PSI / Pumprough check only
Active Source Pumpsrunning
Active Inline Pumpsrunning
Standby / Backup Pumpsnot running

Calculated Hydraulic Outputs

FlowBPD / GPM
Velocity Per Line
Line Volumebbl in hose/pipe
Friction Headft / psi
Total Head incl. Elevationft / psi
Hydraulic HP Required
Pressure Capacity Check

4. Equipment & Operating Inputs

Hose Cost$/ft/day
Pump Cost$/pump/day
Automation / Telemetry Units
Flow Meters
Manifolds
Light Towers
Filter Pods
Other Daily Equipment$/day

5. Labor, Fuel & Transportation Inputs

Labor
Operators / Shiftcount
Shifts / Daycount
Hours / Shifthours
Operator Labor Rate$/hr
Supervisor Daysdays
Supervisor Day Rate$/day
Per Diem / Person$/day
Lodging Rooms / Dayrooms
Lodging / Room$/night
Crew Trucks
Fuel & Transportation
Operating Hours / Dayhours
Pump Fuel Burngal/hr/running pump
Diesel Price$/gal
Generator Countcount
Generator Fuel Burngal/hr/unit
Transport Truckscount
One-Way Travel Timehours
Round Trip Factorone-way × factor
Truck Rate$/hr
Transport Misc.$ lump sum

6. Rig-Up / Rig-Down & Third-Party Inputs

Rig-Up Cost / Mile$/linear mile
Rig-Down Cost / Mile$/linear mile
Road Crossing Cost$/crossing
Pressure Test / Commissioning$ lump sum
Permits / ROW / Survey$ lump sum
Spotters / Guards / Traffic$/day
Rig-Up Misc.$ lump sum
Rig-Down Cleanup / Misc.$ lump sum

7. Proposal Pricing Controls

Pricing ControlEditable InputMeaning Pricing ControlEditable InputMeaning
Rig-Up Target Margin% margin on rig-up section Operations Target Margin% margin on operating section
Rig-Down Target Margin% margin on rig-down section Daily Rate Adjustment% adjustment to operations price
Final Proposal Adjustment% adjustment to final total Round Proposal Tonearest $ increment

8. Calculated Cost Build-Up

Total Job Barrels
Daily Operating Rate
Total Proposal
All-In $/BBL
SectionLine ItemCostProposal PriceUnit / Notes

9. Proposal Summary

Equipment Delivery to Site
Rig-Up Charge
Daily Operating Rate
Operating Days
Rig-Down Charge
Equipment Demobilization from Site
Total Estimated Job Charge
All-In Price / Barrel
Operating-Only Price / Barrel
Gross Margin

10. Sensitivity View

ScenarioFlow BPMTarget MarginDaily RateTotal Proposal$/BBL
Sensitivity changes flow and operating margin only. All other inputs stay as entered.

11. Internal Scope Discipline Notes

CheckYes / No / N.A.Notes
Route walked / confirmed
Hydraulic review completed
Operations resource availability confirmed
Customer fuel responsibility confirmed
Open items / exclusions